Expansion Project - Phase 1 Cost Overview Print E-mail

Total Contract Amount (including tax):
$326,700.00

Up to date change orders (including tax)*:
$19,324.60

Adjusted contract amount (including change orders plus tax):
$346,024.60

Payment upto date (including change orders plus tax):
$282,701.01

REMAINING CONTRACT AMOUNT (Including tax):
$63,323.59

OTHER EXPENSES PAID

(Electric,Carpentary,Plumbing,Permits, Sport courts, Utilities)
$24,973.97

EXPECTED ADDITIONAL CHANGE ORDERS (including irrigation & Landscaping)
$10,000.00

Total
$380,998.57

PHASE II ESTIMATED COST
$320,000.00
* Change orders pays for extra work needed to complete the project and it was not included in the scope of work in the contract.